Gateway Expressway

> Gateway Expressway

Gateway Expressway

Gateway Expressway

Client: Cardno, Inc., FDOT District 7
Location: Pinellas County, FL
Size: Length: 12 miles |  Construction Cost: $544 million
Service: Genesis CEI Services

Highlights:
Contact Staff: Marty Sanchez, P.E.
 

Genesis CEI is a major subconsultant on the 1,300-day Gateway Expressway design-build project in Pinellas County. It will take over $544 million to construct over 12 miles of bridges, flyovers, and roadways. This project is complex and includes several components and upgrades to the existing roadway system:

  • SR 690 will be a new elevated 4-lane expressway connection from US 19 to west of I-275.
  • SR 686A will be a new elevated 4-lane elevated expressway from the Bayside Bridge to just west of I-275 that will merge with SR 690 via flyover structures.
  • SR 686 (Roosevelt Boulevard) will be reconstructed from the Bayside Bridge to SR 688 (Ulmerton Road) as a 2-lane road with new access to the St. Pete-Clearwater International Airport.
  • CR 296 (118th Avenue) will reconstructed from US 19 to 31st Court North. I-275 will be reconstructed from South of Gandy Boulevard to North of 4th Street North.  

All elevated roadways will be managed toll lanes. The Gateway Expressway project is the largest project ever undertaken by FDOT District 7. When completed, this project will result in a significant positive impact to the region.

www.GenesisGroup.com

Gateway Expressway


Pinellas County, FL

Client:

Cardno, Inc., FDOT District 7

Location:

Pinellas County, FL

Size:

Length: 12 miles |  Construction Cost: $544 million

Service

Genesis CEI Services

Highlights:

Construction Engineering and Inspection

Contact Staff:

Marty Sanchez, P.E.

Gateway Expressway

Genesis CEI is a major subconsultant on the 1,300-day Gateway Expressway design-build project in Pinellas County. It will take over $544 million to construct over 12 miles of bridges, flyovers, and roadways. This project is complex and includes several components and upgrades to the existing roadway system:

  • SR 690 will be a new elevated 4-lane expressway connection from US 19 to west of I-275.
  • SR 686A will be a new elevated 4-lane elevated expressway from the Bayside Bridge to just west of I-275 that will merge with SR 690 via flyover structures.
  • SR 686 (Roosevelt Boulevard) will be reconstructed from the Bayside Bridge to SR 688 (Ulmerton Road) as a 2-lane road with new access to the St. Pete-Clearwater International Airport.
  • CR 296 (118th Avenue) will reconstructed from US 19 to 31st Court North. I-275 will be reconstructed from South of Gandy Boulevard to North of 4th Street North.  

All elevated roadways will be managed toll lanes. The Gateway Expressway project is the largest project ever undertaken by FDOT District 7. When completed, this project will result in a significant positive impact to the region.